Transfer System
- Excavate and pour all tower footings
- Furnish and install 15 two leg towers
- Furnish and install 3 four leg towers
- Furnish and install 862 ft of pipe rack
- Install piping on top of pipe rack
- Excavate and pour bag house foundation
- Install bag house
- Furnishing and install transfer system to transfer DDG from the south side of the plant to the north
- Install 3 conveyors
Project Details
In Progress
ServiceAgricultural Construction, Millwright Services
Project Time Frame02/03/2021 - LocationIllinois